The top panel will be fabricated in one work session. The setup, fabrication, and vacuum bagging time is ~180 minutes. The part must remain in an appropriated ventilated area while under vacuum for the specified curing time. Once cured, the sealed part may be removed and placed into the NER bay for ~1 week to fully cure.

Left Sidepod [3 hrs active, 1 week passive

...

]

The left sidepod will be fabricated in one work session. The setup, fabrication, and vacuum bagging time is ~180 minutes. The part must remain in an appropriated ventilated area while under vacuum for the specified curing time. Once cured, the sealed part may be removed and placed into the NER bay for ~1 week to fully cure.

Right Sidepod [3 hrs active, 1 week passive]

The right sidepod will be fabricated in one work session. The setup, fabrication, and vacuum bagging time is ~180 minutes. The part must remain in an appropriated ventilated area while under vacuum for the specified curing time. Once cured, the sealed part may be removed and placed into the NER bay for ~1 week to fully cure.

...