For general purchasing stuff, please look at the Finance Team pages. This page will serve as a summary on the general process we have for purchasing stuff for engineering projects
CONTENTS
BOMs
All projects have a Bill of Materials (BOM) spreadsheet in their Google Drive folder (which should also be linked in Confluence). This spreadsheet should itemize every purchase that ever needs to be made relating to a project.
The one exception we have to this currently is PCBs, in which case we utilize the Altium ActiveBOM system, and instead add the entire PCB cost to the project BOM in Google Drive
Most columns are explanatory. WBS is the work breakdown structure for the work package. We’ve somewhat retired this column as we now budget for projects as a whole (X.X.0) as opposed to a specific WP (X.X.X).
Pooled Purchases
We make a lot of purchases. To save money on shipping costs, consolidate packages, and reduce finance forms, it is helpful to pool orders!
We currently have two spreadsheets to pool the following:
McMaster-Carr: https://docs.google.com/spreadsheets/d/1kqpnw8jZDx2GO5NFUtqefRXqT1XX46iMx5ZI4euPJgY/edit#gid=0
EE Distributors: https://docs.google.com/spreadsheets/d/1YDD7SfCvcUX-2A0aKgKVb-ZtQCIAu4mKnFacT-Uho7E/edit#gid=0
Digikey
Mouser
Arrow
Newark
etc
Adding Stuff to be Purchased
Add your item to the project BOM
When ready to order, add your item to the appropriate order sheet
Make sure to paste without formatting (Ctrl + Shift + V)
Include the correct WBS for the project (http://finishlinebyner.com)
Order!
If you are in no rush, just let it sit until someone places an order
If you need it soon, place the order yourself! (see section below)
Making the Purchase
If you need something ASAP, or the spreadsheet has built up, it’s time to buy!
Purchasing from McMaster
blah blah
Purchasing from Digikey
blah blah